Scaffolding

Around the generator of unit EC3.
Same happens at unit EC 7.
In one hour an expert will arrive to do an inspection at the inside of the generators.
Just to make sure we don't get the same problems like at unit EC 4....

So we had to blow off the hydrogen (coolant) out of the generator bij means of carbondioxide (CO2) en later the CO2 by air.
After that we can give the sign "all safe".

Seen from the casing of the low pressure turbine.
The scaffolding is done to give access to the manholes on top.

Better in LARGE...

Comments
Sign in or get an account to comment.