installing floor joist and yellow tongue

Issues
1. Yesterday we lost half a day of work due to the posi struts being delivered 3hours late. The carpenter didnt stick around and left the site after fixing the frame to the steel.

2. It was a scorching 40degrees today so we lost another half a day of work. Carpenters left the site at 1130 but were able to get most of the posi struts up and the yellow tongue hoisted up on to the floor joist.

Tomorrow should be a better day with the weather forecasted to be 29degrees and sunny.