Bathroom stage 5
Earlier stages:
here,
here and
here.
Since then, a great deal of work, but not much to show.
Now - insulation in the walls (pink for thermal on the exterior walls and green for noise reduction on the interior walls), wall cabinet installed (rebated into the wall cavity - doors currently off), shower tray installed, plumbing all done and a ceiling!
Next stage - plasterboard (dry wall) on the walls.