Blob the Builder

By Blobinski

Game of Two Halves

2nd half of the garage slab all prepped, squared, and levelled, ready for Monday morning concrete delivery. At 6 x 4m it's the same as last Monday's pour. In the foreground is formwork for steps, for the excess concrete, as we have to take the full 4m3 load. Weather forecast milder, though looking wet. Day off tomorrow!